What is the general rule for containment during lead jobs?

Prepare for the California State Lead Supervisor Exam. Use our comprehensive study tools with flashcards and multiple-choice questions. Ensure success on your exam day!

The general rule for containment during lead jobs requires the use of a single layer of 6 mil polyethylene sheeting that extends 10 feet in all directions from the work area. This standard is designed to effectively contain lead dust and debris generated during work, ensuring that it does not escape the designated containment zone and pose a risk to workers and the surrounding environment.

The 6 mil thickness provides an adequate barrier to prevent the passage of lead particles, which can be hazardous to health. Extending the containment area by 10 feet helps to capture any potential lead dust that may migrate from the immediate work site during activities such as sanding, cutting, or demolition. This guideline balances effective containment with practical considerations for worksite size and layout, ensuring safety while maintaining efficiency in lead-related projects.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy